This procedure allows you to establish the contract start date, end date, curve, and Units of Measurement (UOM) for all the contract line items.
-
Navigate to Budgets > Contract Budget.
-
At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required project.
-
If required, click REFRESH to update the screen.
-
Click the Contract Budget Register tab.
-
Populate data as indicated below:
-
(Optional) Start Date
-
(Optional) End Date
-
(Optional) Click the Curve ellipsis to select the budget curve. Budget curves include:
-
Back Loaded
-
Bell Curve
-
Front Loaded
-
Linear
-
Manual
-
-
(Optional) UOM
-
Click the Save icon.
You can customize the view of the Line Item Register panel from the view settings.
-