The Related RFIs tab is used to relate a contract change to one or more RFIs available in EcoSys Contracts.

  1. Navigate to Changes > Contract Changes.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.

  3. If required, click REFRESH to update the screen.

  4. Click the Contract Change Register tab.

  5. Click the Contract Change ID hyperlink. The Contract Change Details panel appears.

  6. Click the Related RFIs tab.

  7. Click the Insert Row icon to add a new row.

  8. Click the RFI ID ellipsis to select the required RFI.

    SHARED Tip You can add more than one RFI to a contract change by adding additional row(s).

  9. Click SAVE. The RFI Name, Project ID, and Project Name will auto-populate.