Validate Progress Method Attributes - EcoSys - 3.01 - Help - Hexagon PPM

EcoSys Contracts Help (3.01)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
3.01

Additional set-up is required for the Physical % Complete, Installed Quantities, and Weighted Milestones progress methods.

After set-up is complete updates to a percentage amount (Weighted Milestones and Physical % Complete progress methods) and/or actual quantities (Installed Quantities progress method) must be completed before VOWD is calculated.

Physical % Complete has to be updated each contract period before VOWD is calculated.