The RCM Potential Yearly Savings report shows all equipment that has an associated Risk Assessment or Risk Analysis with a certain Risk Level and that has one or more PM Schedules or Maintenance Patterns attached and activated. Based on the Risk Assessment / Analysis it may be worthwhile to consider not doing any preventive work on the listed equipment. Important report parameters:
Organization: Leave blank for all. Supports wildcards.
RCM Project: Enter the RCM Project.
Equipment: Leave blank for all. Supports wildcards.
Maximum Risk Level: Leave blank for all. If you select a value, the system will only include equipment with the same Risk Level or lower. Lower here means the Rating/Threshold of the included Risk Levels is the same or less than that of the selected Risk Level.
Years Included in Avg.: The average cost calculation of this report uses this parameter to determine how far to go back in history for the cost calculation.